PG&E Streetlight Upgrade Status - Printable Version +- The Terraces (http://forum.ithasf.org) +-- Forum: Announcements (http://forum.ithasf.org/forumdisplay.php?fid=1) +--- Forum: IT Meetings and Events (http://forum.ithasf.org/forumdisplay.php?fid=2) +--- Thread: PG&E Streetlight Upgrade Status (/showthread.php?tid=185) |
PG&E Streetlight Upgrade Status - MarkScardina - 07-19-2018 I have received this update for the PG&E Streetlight upgrade work being completed. 3 week lookahead schedule is as follows: Week of 7/16, we will be starting at the SWCO Urbano/Victoria IFO 744 Urbano, and making our way west down Urbano twds 700 Urbano, and will most likely start on De Soto once we finish on Urbano Week of 7/23 will work on De Soto, then move to Corona St pending progress, restoring the sidewalks on Victoria next week and then up and around Urbano. Week of 7/30 finish up De Soto/Corona If we are able to keep to this schedule, we will be done North of Holloway by 8/6 Regards, Mark |